SIPAG: CONSTRUCTION OF NAMANTAO ROAD, PHASE 2, DARAGA, ALBAY

SIPAG: CONSTRUCTION OF NAMANTAO ROAD, PHASE 2, DARAGA, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱57,881,650.65. Status: Reported complete (DPWH). Contractor on record: A3 CONST. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Tinago Phase 2, Sta. 0 + 250 - Sta. 0 + 450, Camalig, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Albay 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

47 projects · ₱2.1B total · 0 flags

Other projects by this contractor

No sat.

CSSP- CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM- TRIP)- ESPERANZA- PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT, MASBATE (DAAN-LUNGSOD BR.)

Masbate 3rd DEO, Region V

2023₱149.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CSSP- CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM- TRIP)- ESPERANZA- PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT, MASBATE

Masbate 3rd DEO, Region V

2023₱144.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-ESPERANZA-PLACER ROAD LEADING TO PASIAGON BEACH FRONT, BALAY NA BATO AND ESPERANZA SEAPORT

Region V, Region V

2022₱143.9M
Reported complete (DPWH)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONSTRUCTION OF DRAINAGE STRUCTURES IN BRGY. BIGAA, BUYUAN, BONGA, PAWA, BOGTONG,

Region V, Region V

2022₱143.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL IT) - BALUD NATIONAL ROAD CONNECTING BARANGAY DANA

Masbate 2nd DEO, Region V

2024₱113.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORE PROTECTION STRUCTURE, CLAVERIA, MASBATE.

Masbate 1st DEO, Region V

2025₱93.6M
Past target date (DPWH On-Going)
View all 47 projects →

4. Implementation

Contract Amount

₱57,881,650.65

Progress

Reported complete (DPWH)

Start Date

March 4, 2022

Target End

September 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.