Buildings and Facilities17I00043

CONSTRUCTION OF EVACUATION CENTER, GUINDAPUNAN, PALO, LEYTE

CONSTRUCTION OF EVACUATION CENTER, GUINDAPUNAN, PALO, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱30,203,410.00. Status: Reported complete (DPWH). Contractor on record: AAVB CONST AND SUPPLY. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱30,203,410.00

Progress

Reported complete (DPWH)

Start Date

July 12, 2017

Target End

November 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.