Roads18AD0102

OPENING AND CONCRETING PALALI-TANGILING, BRGY. BANGA FMR, BRGY. BANGA, SUGPON, ILOCOS SUR

OPENING AND CONCRETING PALALI-TANGILING, BRGY. BANGA FMR, BRGY. BANGA, SUGPON, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱4,726,392.06. Status: Reported complete (DPWH). Contractor on record: DJY CONST 35651. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 35651

94 projects · ₱6.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL JCT

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BEYENG - TACADANG ROADBAKUN & KIBUNGAN, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2022₱198.0M
Reported complete (DPWH)
No sat.

KIANGAN - TINOC - BUGUIAS RD - KO355+520 - KO355+668TINOC, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2022₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS GOV. BADO DANGWA NATIONAL ROADK0308+979 - KO309+08

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD, ABINUAN - NATTUM - ALIMIT (MAYOYAO), BARANGAY BOLIWONG, LAGAWE, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2024₱191.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE, PINTO STA.31+800 - STA. 33+650 (L/S) ALFONSO LISTA, IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2025₱190.0M
Past target date (DPWH On-Going)
View all 94 projects →

4. Implementation

Contract Amount

₱4,726,392.06

Progress

Reported complete (DPWH)

Start Date

May 14, 2018

Target End

July 12, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.