Flood Control and Drainage18JA0059

CONSTRUCTION OF DRAINAGE SYSTEM, BUNGUIAO, ZAMBOANGA CITY

CONSTRUCTION OF DRAINAGE SYSTEM, BUNGUIAO, ZAMBOANGA CITY is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱1,960,168.27. Status: Reported complete (DPWH). Contractor on record: ELFCT CONST. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

12 projects · ₱39.6M total · 0 flags

4. Implementation

Contract Amount

₱1,960,168.27

Progress

Reported complete (DPWH)

Start Date

April 4, 2018

Target End

June 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.