Buildings and Facilities22IH0031

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) PHASE II, BARANGAY SAN LUIS, CAPUL, NORTHERN SAMAR

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) PHASE II, BARANGAY SAN LUIS, CAPUL, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱2,939,327.36. Status: Past target date (DPWH On-Going). Contractor on record: CHRISTFER CONST. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Phase II, Barangay Bangon, Gamay, Northern Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Northern Samar 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,939,327.36

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2022

Target End

July 5, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.