Construction of Flood Mitigation Structure22IJ0045

Construction of Flood Control Structures along Sinidman River (Upstream) Phase II, Brgy. Sinidman Occidental, Calbayog City, Samar

Construction of Flood Control Structures along Sinidman River (Upstream) Phase II, Brgy. Sinidman Occidental, Calbayog City, Samar is a DPWH-tracked public work in CALBAYOG CITY (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIII. Reported contract value: ₱48,603,252.18. Status: Reported complete (DPWH). Contractor on record: PABLO S LABASBAS CONST CORP FORMERLY: PABLOS LABASBAS CONST CORP. Figures trace to sumbong.

CALBAYOG CITY (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Sinidman River (Upstream) Phase II, Brgy. Sinidman Occidental, Calbayog City, Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003145

₱185,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. SUROK - GAHOY - SAPAO, GUIUAN, EASTERN SAMAR

Region VIII, Region VIII

2023₱144.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TACLOBAN - STA. FE - SAN MIGUEL ROAD, LEYTE

Region VIII, Region VIII

2023₱143.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE ALONG ASUNCION - BENIT SECTION, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱120.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY NUEVA ESPERANZA, HINUNANGAN, SOUTHERN LEYTE

Southern Leyte 2nd DEO, Region VIII

2025₱105.6M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING SECONDARY ROADS, WRIGHT - TAFT - BORONGAN RD (SM00172SM)K0875+667 - K0876+511, K0877+525 - K0878+256, K0878+800 - K0879+389

Eastern Samar DEO, Region VIII

2025₱104.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BAGAHUPI - BABATNGON - STA CRUZ - BARUGO - CARIGARA RD. - (S00066LT) K0927+(-348) - K0927+(-310), LEYTE 1ST LD

Region VIII, Region VIII

2023₱101.2M
Reported complete (DPWH)
View all 515 projects →

4. Implementation

Contract Amount

₱48,603,252.18

Progress

Reported complete (DPWH)

Start Date

February 8, 2022

Target End

September 28, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.