Flood Control and Drainage18CN0055

REPAIR/REHABILITATION/RESTORATION/IMPROVEMENT OF DAMAGEDC FLOOD CONTROL PROJECT, BRGY. SAN ISIDRO, SAN LUIS, AURORA

REPAIR/REHABILITATION/RESTORATION/IMPROVEMENT OF DAMAGEDC FLOOD CONTROL PROJECT, BRGY. SAN ISIDRO, SAN LUIS, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱4,189,567.50. Status: Reported complete (DPWH). Contractor on record: IRC CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱2,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Project, Bugayong Creek, Brgy. Paleg, Dinalungan, Aurora Province
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Aurora DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,189,567.50

Progress

Reported complete (DPWH)

Start Date

May 4, 2018

Target End

July 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.