Roads25OI0007

PREVENTIVE MAINTENANCE - SECONDARY ROADS: ZAPOTE - ALABANG RD, K0021+795 - K0022+332, LAS PINAS CITY

PREVENTIVE MAINTENANCE - SECONDARY ROADS: ZAPOTE - ALABANG RD, K0021+795 - K0022+332, LAS PINAS CITY is a DPWH-tracked public work in Las Piñas-Muntinlupa DEO, National Capital Region. Reported contract value: ₱37,619,880.72. Status: Reported complete (DPWH). Contractor on record: I&E CONST CORP FORMERLY: I&E CONSTR. Figures trace to dpwh.

Las Piñas-Muntinlupa DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Upper Palico, Kabulusan 1, Cupang, Muntinlupa City (Phase 2)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Las Piñas-Muntinlupa DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

165 projects · ₱10.9B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MISSING LINKS/ NEW ROADS GENERAL NAKAR - DINGALAN ROAD (GEN. NAKAR SIDE), PACKAGE A, QUEZON

Region IV-A, Region IV-A

2022₱289.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 2, BACOOR, CAVITE

Region IV-A, Region IV-A

2025₱280.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)IMUS-BACOOR LINK ROAD, PACKAGE 1, BACOOR, CAVITE

Region IV-A, Region IV-A

2025₱280.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURES AND OTHER IMPROVEMENTS AT BARANGAYS TALON 1 TO TALON 3, LAS PINAS CITY

Las Piñas-Muntinlupa DEO, National Capital Region

2025₱218.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF BASUD-LANOT ROAD, BASUD,

Region V, Region V

2024₱187.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF DAET-SAN VICENTE-SAN LOR

Region V, Region V

2024₱183.3M
Past target date (DPWH On-Going)
View all 165 projects →

4. Implementation

Contract Amount

₱37,619,880.72

Progress

Reported complete (DPWH)

Start Date

March 14, 2025

Target End

April 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.