Flood Control and Drainage25CP0041

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SALACOT - ILOG BULO CONCRETE SLOPE PROTECTION ALONG BULO RIVER SECTION, SAN MIGUEL, BULACAN (UPSTREAM DIKE, PACKAGE 1)

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SALACOT - ILOG BULO CONCRETE SLOPE PROTECTION ALONG BULO RIVER SECTION, SAN MIGUEL, BULACAN (UPSTREAM DIKE, PACKAGE 1) is a DPWH-tracked public work in Bulacan 3rd DEO, Region III. Reported contract value: ₱47,525,402.34. Status: Past target date (DPWH On-Going). Contractor on record: FLORDES CONST. Figures trace to dpwh.

Bulacan 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Meycauayan River and its tributaries (Deca Homes Section), Barangay Saluysoy, Meycauayan City, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

333 projects · ₱17.6B total · 0 flags

4. Implementation

Contract Amount

₱47,525,402.34

Progress

Past target date (DPWH On-Going)

Start Date

June 1, 2025

Target End

December 27, 2025

5. Audit