Flood Control and Drainage23AA0112

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL MMITIGATION STRUCTURE ALONG PADSAN RIVER GOING DOWNSTREAM RIGHT SIDE, BARANGAY TALINGAAN (PHASE I), LAOAG CITY, ILOCOS NORTE

CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL MMITIGATION STRUCTURE ALONG PADSAN RIVER GOING DOWNSTREAM RIGHT SIDE, BARANGAY TALINGAAN (PHASE I), LAOAG CITY, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱80,748,341.14. Status: Past target date (DPWH On-Going). Contractor on record: VIKING CONST & SUPPLIES. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Mitigation Structure along Padsan River going Downstream Right Side, Barangay Talingaan (Phase II), Laoag City, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

53 projects · ₱3.1B total · 0 flags

Other projects by this contractor

View all 53 projects →

4. Implementation

Contract Amount

₱80,748,341.14

Progress

Past target date (DPWH On-Going)

Start Date

March 13, 2023

Target End

January 13, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.