Roads21K00026

CONSTRUCTION OF BYPASS AND DIVERSION ROADS, SAYRE HIGHWAY PARALLEL ROAD II, (NABAG-O JCT. VALENCIA-KAPALONG-TALAINGOD SAN ISIDRO SECTION), BUKIDNON

CONSTRUCTION OF BYPASS AND DIVERSION ROADS, SAYRE HIGHWAY PARALLEL ROAD II, (NABAG-O JCT. VALENCIA-KAPALONG-TALAINGOD SAN ISIDRO SECTION), BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱119,044,363.18. Status: Reported complete (DPWH). Contractor on record: M MONTESCLAROS ENT INC 6506. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱119,044,363.18

Progress

Reported complete (DPWH)

Start Date

March 15, 2021

Target End

January 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.