Buildings and Facilities21BH0135

REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PAPAN ESTE

REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PAPAN ESTE is a DPWH-tracked public work in Isabela 4th DEO, Region II. Reported contract value: ₱1,980,000.00. Status: Reported complete (DPWH). Contractor on record: COLBY CONST. Figures trace to dpwh.

Isabela 4th DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Drainage, Barangay Rizaluna, Cordon, Isabela
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Isabela 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

106 projects · ₱2.2B total · 0 flags

Other projects by this contractor

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING /FACILITIES - CONSTRUCTION DABUBU PEQUEÑO FLOOD CONTROL STRUCTURE, STA. 0+000-STA.0+790, SAN AGUSTIN, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF AYOD FLOOD CONTROL STRUCTURE, SECTION 1, DINAPIGUE, ISABELA

Isabela 4th DEO, Region II

2024₱96.5M
Reported complete (DPWH)

Construction of Barangay Virgoneza Flood Control Structure, Section 2, San Agustin, Isabela

SAN AGUSTIN (ISABELA), ISABELA, Region II

2023₱96.5M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEM - CONSTRUCTION OF BARANGAY SINAOANGAN SUR FLOOD CONTROL STRUCTURE, SECTIO

Isabela 4th DEO, Region II

2023₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING /FACILITIES - CONSTRUCTION OF PAYAC FLOOD CONTROL STRUCTURE, STA. 0+000 - STA. 0+700, JONES, ISABELA

Isabela 4th DEO, Region II

2024₱96.0M
Past target date (DPWH On-Going)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) ALFONSO LISTA - AURORA BDRY. ROAD - K0452 + 392 - K0453 + 849, KO453 + 950 - KO454 + 993

Ifugao 2nd DEO, Cordillera Administrative Region

2017₱95.9M
Reported complete (DPWH)
View all 106 projects →

4. Implementation

Contract Amount

₱1,980,000.00

Progress

Reported complete (DPWH)

Start Date

May 3, 2021

Target End

July 26, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.