Bridges18KL0048

WIDENING OF PERMANENT BRIDGE, SAN ANTONIO BRIDGE (B01111MN) ALONG BUTUAN CITY-CAGAYAN DE ORO CITY-IL

WIDENING OF PERMANENT BRIDGE, SAN ANTONIO BRIDGE (B01111MN) ALONG BUTUAN CITY-CAGAYAN DE ORO CITY-IL is a DPWH-tracked public work in Misamis Oriental 2nd DEO, Region X. Reported contract value: ₱27,278,093.51. Status: Reported complete (DPWH). Contractor on record: DICON BUILDERS CORP 33181. Figures trace to dpwh.

Misamis Oriental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱27,278,093.51

Progress

Reported complete (DPWH)

Start Date

February 12, 2018

Target End

July 31, 2018

5. Audit