GAA 2025 DEPED BEFF25MD0075

CONSTRUCTION OF SCHOOL BUILDING, DEL PILAR ELEMENTARY SCHOOL, BARANGAY RANGAYEN, ALAMADA, COTABATO

CONSTRUCTION OF SCHOOL BUILDING, DEL PILAR ELEMENTARY SCHOOL, BARANGAY RANGAYEN, ALAMADA, COTABATO is a DPWH-tracked public work in Cotabato 1st DEO, Region XII. Reported contract value: ₱4,199,377.86. Status: Past target date (DPWH On-Going). Contractor on record: LIMSA CONST AND SUPPLY 51941. Figures trace to dpwh.

Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Capayuran, Pigcawayan, North Cotabato
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cotabato 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,199,377.86

Progress

Past target date (DPWH On-Going)

Start Date

September 8, 2025

Target End

December 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.