GAA 2025 DA FMR25HA0112

CONCRETING OF BRGY. SAN ISIDRO TO BRGY. LIBERTAD FMR, SAN ISIDRO, BACLAYON, BOHOL

CONCRETING OF BRGY. SAN ISIDRO TO BRGY. LIBERTAD FMR, SAN ISIDRO, BACLAYON, BOHOL is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱10,979,720.00. Status: Past target date (DPWH On-Going). Contractor on record: IMPREZA CONST SERVICES 47486. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Protection Dike, Cahayag CIS, Tubigon, Bohol
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bohol 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱10,979,720.00

Progress

Past target date (DPWH On-Going)

Start Date

May 28, 2025

Target End

October 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.