Buildings and Facilities20GH0119

CONSTRUCTION OF MULTIPURPOSE BUILDING (MARKET DEVELOPMENT) AT ZONE 1, BRGY. POBLACION, ESTANCIA, ILOILO

CONSTRUCTION OF MULTIPURPOSE BUILDING (MARKET DEVELOPMENT) AT ZONE 1, BRGY. POBLACION, ESTANCIA, ILOILO is a DPWH-tracked public work in Iloilo 3rd DEO, Region VI. Reported contract value: ₱5,869,257.69. Status: Reported complete (DPWH). Contractor on record: WINCES CONST. Figures trace to dpwh.

Iloilo 3rd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,869,257.69

Progress

Reported complete (DPWH)

Start Date

December 13, 2020

Target End

July 10, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.