Buildings and Facilities17BK0137

CONSTRUCTION OF ONE-STOREY TWO CLASSROOM SCHOOL BUILDING, DIORYONG INTEGRATED SCHOOL, NAGTIPUNAN, QUIRINO

CONSTRUCTION OF ONE-STOREY TWO CLASSROOM SCHOOL BUILDING, DIORYONG INTEGRATED SCHOOL, NAGTIPUNAN, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱2,713,364.94. Status: Reported complete (DPWH). Contractor on record: JMD-68 BUILDERS. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

217 projects · ₱738.9M total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF CAGAYAN RIVER FLOOD CONCTROL (STO. NIÑO SECTION), MADDELA, QUIRINO

Quirino DEO, Region II

2025₱28.1M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAN MARCOS, CABARROGUIS, QUIRINO

Quirino DEO, Region II

2023₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS ( TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - ACCESS ROAD LEADING TO PEDLISAN FALLS, MADDELA, QUIRINO

Quirino DEO, Region II

2024₱19.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM- TRIP) ACCESS ROAD LEADING TO ASAKLAT CAVES, NAGTIPUNAN, QUIRINO

Quirino DEO, Region II

2024₱14.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROAD LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM ROLL-IT) RAMOS - SAN RAMON ROAD CONNECTING FEEDS

Quirino DEO, Region II

2024₱14.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (PLENARY HALL) SAN MARCOS, CABARROGUIS, QUIRINO

Quirino DEO, Region II

2021₱11.9M
Reported complete (DPWH)
View all 217 projects →

4. Implementation

Contract Amount

₱2,713,364.94

Progress

Reported complete (DPWH)

Start Date

December 14, 2017

Target End

March 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.