Roads18LD0073

CONCRETING OF JUNCTION NATIONAL HIGHWAY, JCT. TO SITIO DIKE, RIZAL-NEW CEBU-NEW CLARIN, BANSALAN, DAVAO DEL SUR

CONCRETING OF JUNCTION NATIONAL HIGHWAY, JCT. TO SITIO DIKE, RIZAL-NEW CEBU-NEW CLARIN, BANSALAN, DAVAO DEL SUR is a DPWH-tracked public work in Davao del Sur DEO, Region XI. Reported contract value: ₱46,802,536.55. Status: Reported complete (DPWH). Contractor on record: HI-VIEW RESOURCES & DEVELOPMENT CORP. Figures trace to dpwh.

Davao del Sur DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Concrete Revetment along Cebulan River, Sta. Cruz, Davao del Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-LGRCB-18-0025292

₱50,900,000.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱46,802,536.55

Progress

Reported complete (DPWH)

Start Date

April 2, 2018

Target End

August 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.