Roads22FE0045

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CAPUCNASAN ROAD, BRGY. CAPUCNASAN, MILAOR, CAMARINES SUR

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF CAPUCNASAN ROAD, BRGY. CAPUCNASAN, MILAOR, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 2nd DEO, Region V. Reported contract value: ₱19,206,333.86. Status: Reported complete (DPWH). Contractor on record: SHLA CONST AND SUPPLY 45590. Figures trace to dpwh.

Camarines Sur 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System of Mahaba Creek leading to Tambang River, Sitio Palayan, Brgy. Lamon, Goa, Camarines Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Camarines Sur 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 45590

81 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

OO1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 5), PILI, CAMARINES SUR (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2022₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), DPWH CAMARINES SUR 2ND DEO, SAN GABRIEL, PAMPLONA, CAMARINES SUR

Camarines Sur 2nd DEO, Region V

2024₱47.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG ROLANDO R. ANDAYA HIGHWAY - K0282 + (-916) - K0282 + (-660), K0282 + (-531) - K0282 + (-458), K0282 + (-406) - K0282 + (-365), K0282 + (-203) - K0282 + (-139), K0282 +

Camarines Sur 1st DEO, Region V

2025₱47.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-VIRAC-BATO-BATALAY-BOTE-BITAOGAN-CARORIAN-CAGRARAY-RADAR STATION ROADS LEADING TO MARIBINA

Region V, Region V

2024₱46.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-MAHARLIKA HIGHWAY-K0415+360-K0415+780, PAMPLONA, CAMARINES SUR (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2025₱42.4M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS ALONG ROLANDO R. ANDAYA HIGHWAY - K0283 + 000 - K0283 + 109, K0283 + 480 - K0283 + 671, K0284 + 000 - K0284 + 214, K0284 + 493 - K0284 + 787, DEL GALLEGO, CAMARINES SUR

Camarines Sur 1st DEO, Region V

2025₱41.0M
Past target date (DPWH On-Going)
View all 81 projects →

4. Implementation

Contract Amount

₱19,206,333.86

Progress

Reported complete (DPWH)

Start Date

March 16, 2022

Target End

July 14, 2022

5. Audit