Flood Control and Drainage17FK0015

CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONST./REHAB. OF CUMADCAD RIVER CONTROL, CASTILLA, SORSOGON

CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONST./REHAB. OF CUMADCAD RIVER CONTROL, CASTILLA, SORSOGON is a DPWH-tracked public work in Sorsogon DEO, Region V. Reported contract value: ₱28,459,005.17. Status: Reported complete (DPWH). Contractor on record: ALNINO CONST. Figures trace to dpwh.

Sorsogon DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Osiao Flood Control, Bacon District, Sorsogon City
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0019343

₱311,300.00 · FY2017

Released to Inawayan National Per High School as (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

123 projects · ₱5.4B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)PASACAO-BALATAN TOURISM COASTAL HIGHWAY, PASACAO, CAMARINES SUR, CAMARINES SUR (2ND LEGISLA

Region V, Region V

2023₱125.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0399+243-K0400+614.45, LIBMANAN, CAMARINES SUR (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2022₱119.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - LA MEDALLA-SALVACION-SAN VICENTE DIVERSION ROAD, CAMARINES SUR

Camarines Sur 5th DEO, Region V

2024₱106.3M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY PASS AND DIVERSION ROADS-CASTILLA BY PASS ROAD PACKAGE 3 CASTILLA, SORSOGON

Sorsogon DEO, Region V

2021₱104.0M
Reported complete (DPWH)
No sat.

CONST/IMPRVT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS(TOURISM RD INFRA. PROGRAM-TRIP

Sorsogon 2nd DEO, Region V

2023₱96.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS-CONSTRUCTION OF PASACAO-BALATAN COASTAL ROAD, BRGY. PINAMASAGAN, SAN FERNANDO, CAMARINES SUR, SAN FERNANDO,

Region V, Region V

2020₱96.5M
Reported complete (DPWH)
View all 123 projects →

4. Implementation

Contract Amount

₱28,459,005.17

Progress

Reported complete (DPWH)

Start Date

March 3, 2017

Target End

August 29, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.