LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BACONGHERMOSA, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱2,883,867.00. Status: Reported complete (DPWH). Contractor on record: T G OCAMPO CONST. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,883,867.00

Progress

Reported complete (DPWH)

Start Date

March 2, 2018

Target End

June 2, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.