Flood Control and Drainage17JA0022

CONSTRUCTION OF FLOOD CONTROL AT SINUNUC RIVER, (INCLUDING RIGHT OF WAY ACQUISITION) ZAMBOANGA CITY 1ST LD

CONSTRUCTION OF FLOOD CONTROL AT SINUNUC RIVER, (INCLUDING RIGHT OF WAY ACQUISITION) ZAMBOANGA CITY 1ST LD is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱17,949,906.98. Status: Reported complete (DPWH). Contractor on record: TEDDIE CONST DEVELOPMENT INC. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱17,949,906.98

Progress

Reported complete (DPWH)

Start Date

June 8, 2017

Target End

May 9, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.