CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM, PUROK 2, BARANGAY UPPER LABAY, GENERAL SANTOS CITY, SOUTH COTABATO

CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM, PUROK 2, BARANGAY UPPER LABAY, GENERAL SANTOS CITY, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱4,818,348.55. Status: Past target date (DPWH On-Going). Contractor on record: BAYTORR CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, ( Concrete Revetment ) , Sinawal River, Barangay Labangal, General Santos City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

South Cotabato 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,818,348.55

Progress

Past target date (DPWH On-Going)

Start Date

April 7, 2025

Target End

August 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.