Bridges20A00228

TULAY NG PANGULO PARA SA KAUNLARANG PANG-AGRARYO (TPKP) : CONSTRUCTION OF STA. MONICA-STA. RITA BRIDGE

TULAY NG PANGULO PARA SA KAUNLARANG PANG-AGRARYO (TPKP) : CONSTRUCTION OF STA. MONICA-STA. RITA BRIDGE is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱8,433,588.17. Status: Reported complete (DPWH). Contractor on record: CHRISTIAN IAN CONST CORP. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱8,433,588.17

Progress

Reported complete (DPWH)

Start Date

January 15, 2021

Target End

December 6, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.