Roads19FJ0051

CONCRETING OF BRGY. SAN ROQUE - BRGY. SOROSIMBAHAN FMR, BRGY. SAN ROQUE AND BRGY. SOROSIMBAHAN, ESPERANZA, MASBATE

CONCRETING OF BRGY. SAN ROQUE - BRGY. SOROSIMBAHAN FMR, BRGY. SAN ROQUE AND BRGY. SOROSIMBAHAN, ESPERANZA, MASBATE is a DPWH-tracked public work in Masbate 3rd DEO, Region V. Reported contract value: ₱24,378,432.79. Status: Reported complete (DPWH). Contractor on record: EJ CANTORIA CONST. Figures trace to dpwh.

Masbate 3rd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

31 projects · ₱488.0M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - POBLACION-MOROCBOROCAN-GUINHADAP-MAGLAMBONG-STO. NIÑO ROAD (PACKAGE 4), MONREAL, MASBATE.

Masbate 1st DEO, Region V

2024₱49.0M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS- CONSTRUCTION OF SHORE PROTECTION STRUCTURE, CAGAS, SAN JACINTO, MASBATE.

Masbate 1st DEO, Region V

2025₱47.5M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM:LOCAL ROADS AND BRIDGES - LOCAL ROADS-CONSTRUCTION/REPAIR/REHABILITATION IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONSTRUCTION OF CONCRETE ROAD-CONSTRUCTION OF ANTIPOLO-MIABAS ROAD, PALANAS, MASBATE

Masbate 3rd DEO, Region V

2021₱47.0M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS-SAN FERNANDO NORTH RD-K0002+259-K0002+317, K0002+717-K0002+802, K0003+630-K0003+693, K0005+000-K0005+036, K0010+238-K0010+558,K0010+561-K0010+586,K0011+678-K0011+1010.

Masbate 1st DEO, Region V

2024₱42.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM - CONSTRUCTION OF ACCESS ROAD, JUNCTION NATIONAL ROAD, LETADA ST. TO PORT, BARANGAY POBLACION, DISTRICT 1 AND DISTRICT 3, SAN JACINTO, MASBATE.

Masbate 1st DEO, Region V

2024₱29.7M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS, BUENAVISTA- KAWAYAN RD- K0060+000- K0060+539

Masbate 3rd DEO, Region V

2022₱20.5M
Reported complete (DPWH)
View all 31 projects →

4. Implementation

Contract Amount

₱24,378,432.79

Progress

Reported complete (DPWH)

Start Date

December 16, 2019

Target End

April 3, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.