Flood Control and Drainage25M00172

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MALASILA RIVER PACKAGE 3, STA. 0+000 - STA. 0+410 AND STA. 0+425 -STA. 465.2, BARANGAY LUNA NORTE, MAKILALA, COTABATO

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MALASILA RIVER PACKAGE 3, STA. 0+000 - STA. 0+410 AND STA. 0+425 -STA. 465.2, BARANGAY LUNA NORTE, MAKILALA, COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱93,411,920.23. Status: Past target date (DPWH On-Going). Contractor on record: AGONG BUILDERS AND CONST SUPPLY INC. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱93,411,920.23

Progress

Past target date (DPWH On-Going)

Start Date

July 9, 2025

Target End

April 18, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.