Flood Control and Drainage19I00137

REPAIR/REHABILITATION OF BRGY. BAYBAY POB. FLOOD CONTROL, SULAT, EASTERN SAMAR

REPAIR/REHABILITATION OF BRGY. BAYBAY POB. FLOOD CONTROL, SULAT, EASTERN SAMAR is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱30,019,340.00. Status: Past target date (DPWH On-Going). Contractor on record: 888 ACY ENT. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

292 projects · ₱9.1B total · 5 flags

4. Implementation

Contract Amount

₱30,019,340.00

Progress

Past target date (DPWH On-Going)

Start Date

November 26, 2019

Target End

October 31, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.