Buildings and Facilities16HI0016

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MOABOG, PILAR, CEBU

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. MOABOG, PILAR, CEBU is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱2,585,345.22. Status: Reported complete (DPWH). Contractor on record: R U AQUINO CONST AND DEVELOPMENT CORP FO 23507. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 23507

133 projects · ₱12.5B total · 0 flags

4. Implementation

Contract Amount

₱2,585,345.22

Progress

Reported complete (DPWH)

Start Date

March 10, 2016

Target End

June 7, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.