Flood Control and Drainage20L00068

CONSTRUCTION OF TAGUM-LIBUGANON FLOOD CONTROL, MABANTAO SECTION, KAPALONG, DAVAO DEL NORTE

CONSTRUCTION OF TAGUM-LIBUGANON FLOOD CONTROL, MABANTAO SECTION, KAPALONG, DAVAO DEL NORTE is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱57,897,330.58. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST 16712. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱57,897,330.58

Progress

Reported complete (DPWH)

Start Date

March 24, 2020

Target End

February 20, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.