Flood Control and Drainage19AD0062

CONSTRUCTION/REHAB OF FLOOD MITIGATION FACILITIES WITH MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF AMBURAYAN RIVER CONTROL (ALILEM SECTION), ALILEM, ILOCOS SUR

CONSTRUCTION/REHAB OF FLOOD MITIGATION FACILITIES WITH MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF AMBURAYAN RIVER CONTROL (ALILEM SECTION), ALILEM, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱37,624,024.83. Status: Reported complete (DPWH). Contractor on record: VILLAR GEN CONST AND SUPPLIES 22540. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 22540

446 projects · ₱6.4B total · 0 flags

4. Implementation

Contract Amount

₱37,624,024.83

Progress

Reported complete (DPWH)

Start Date

June 3, 2019

Target End

January 30, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.