Roads21JC0016

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2032 + 212.62 - K2032 + 243.2, ZN.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2032 + 212.62 - K2032 + 243.2, ZN. is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: ROAD EDGE TRADING. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱4,200,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Kauswagan, Sergio Osmena, Zamboanga del Norte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Zamboanga del Norte 3rd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

223 projects · ₱12.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE, BARANGAY GUINACUTAN, VINZ

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE ALONG CULASI, BARANGAY PAM

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER, BANTACAN, NEW BATAAN, DAVAO DE ORO

Davao de Oro 2nd DEO, Region XI

2024₱144.7M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PORT BARTON-TDC ROAD SECTION, STA. 017+770-STA. 017+865; STA. 017+914-STA. 017+969; STA. 018+023-STA. 018+244, PALAWAN

Region IV-B, Region IV-B

2022₱144.5M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1398 + 300- K1398 + 600

Misamis Oriental 1st DEO, Region X

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF DRAINAGE SYSTEM ALONG DAGUPAN ST., MANILA CITY, PHASE 1

North Manila DEO, National Capital Region

2025₱140.3M
Past target date (DPWH On-Going)
View all 223 projects →

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 23, 2021

Target End

December 24, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.