Flood Control and Drainage20BA0038

CONSTRUCTION OF CABUGAO FLOOD CONTROL, BRGY. POBLACION, UYUGAN, BATANES

CONSTRUCTION OF CABUGAO FLOOD CONTROL, BRGY. POBLACION, UYUGAN, BATANES is a DPWH-tracked public work in Batanes DEO, Region II. Reported contract value: ₱1,862,007.16. Status: Reported complete (DPWH). Contractor on record: R L PACANA'S CONST. Figures trace to dpwh.

Batanes DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,862,007.16

Progress

Reported complete (DPWH)

Start Date

February 19, 2020

Target End

April 23, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.