Buildings and Facilities16DF0173

CONSTRUCTION OF CLASSROOMS - CONSTRUCTION OF 4STY 12CL SCHOOL BUILDING AT SHS IN CARMONA, CARMONA

CONSTRUCTION OF CLASSROOMS - CONSTRUCTION OF 4STY 12CL SCHOOL BUILDING AT SHS IN CARMONA, CARMONA is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱21,487,817.61. Status: Reported complete (DPWH). Contractor on record: OMNICON BUILDERS. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Brgy. Lantic, Carmona, Cavite
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-16-0027749

₱8,540,498.00 · FY2016

Released to Division of Sorsogon (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱21,487,817.61

Progress

Reported complete (DPWH)

Start Date

July 13, 2016

Target End

January 23, 2017

5. Audit