Buildings and Facilities20IH0077

CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. LOWER CAYNAGA, LOPE DE VEGA, NORTHEN SAMAR

CONSTRUCTION OF MULTIPURPOSE BUILDING, BRGY. LOWER CAYNAGA, LOPE DE VEGA, NORTHEN SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱1,618,837.99. Status: Reported complete (DPWH). Contractor on record: NG2 CONST CORP 42912. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,618,837.99

Progress

Reported complete (DPWH)

Start Date

February 15, 2021

Target End

April 15, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.