Roads24J00308

REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED ALONG MAIMBUNG-PARANG ROAD, MAIMBUNG, SULU

REHABILITATION/RECONSTRUCTION OF DAMAGED PAVED ALONG MAIMBUNG-PARANG ROAD, MAIMBUNG, SULU is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱24,120,767.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: MRI CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱24,120,767.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 2, 2025

Target End

September 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.