Flood Control and Drainage19CB0018

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DIKE TUYO RIVER, BALANGA CITY, BATAAN

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF DIKE TUYO RIVER, BALANGA CITY, BATAAN is a DPWH-tracked public work in Bataan 2nd DEO, Region III. Reported contract value: ₱14,699,971.59. Status: Reported complete (DPWH). Contractor on record: JEPA CONST. Figures trace to dpwh.

Bataan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱14,699,971.59

Progress

Reported complete (DPWH)

Start Date

June 4, 2019

Target End

October 21, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.