Flood Control and Drainage18BG0048

CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJET, PULAY, LUNA, ISABELA, STA. 0+000 - STA. 0+172.40

CONSTRUCTION OF MAGAT RIVER FLOOD CONTROL PROJET, PULAY, LUNA, ISABELA, STA. 0+000 - STA. 0+172.40 is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱27,914,673.35. Status: Reported complete (DPWH). Contractor on record: DANYSONS CONST AND DEVELOPMENT CORP FORMERLY: DANYSONS CONST 25452. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 25452

114 projects · ₱2.8B total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ROXAS BYPASS ROAD, ISABELA, ROXAS, ISABELA

Isabela 2nd DEO, Region II

2019₱108.6M
Reported complete (DPWH)
No sat.

NETWORK DEV'T: IMPV'T/WIDENING OF NAT'L RDS. ALONG NAT'L RD 1 (N1) DAANG MAHARLIKA/ASIAN HIGHWAY-26

Region II, Region II

2016₱105.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ALICIA-ANGADANAN-SAN GUILLERMO-CAUAYAN CITY-NAGUILIAN ALTERNATE ROUTE, PACKAGE 1, ISABELA

Region II, Region II

2023₱99.4M
Reported complete (DPWH)
No sat.

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL PROJECT ALONG GANANO RIVER, BARANGAY DAGUPAN, ALICIA, ISABELA

Isabela 3rd DEO, Region II

2025₱96.4M
Past target date (DPWH On-Going)

OO2:PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS- CONSTRUCTION OF CAGAYAN RIVER FLOOD CONTROL STRUCTURE, BRGY. DISTRICT 2, PHASE3

Isabela 3rd DEO, Region II

2025₱96.4M
Reported complete (DPWH)
No sat.

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SIFFU RIVER FLOOD CONTROL PROJECT, (RIZAL SECTION PHASE II) QUIRINO, ISABELA

Isabela 2nd DEO, Region II

2025₱96.4M
Past target date (DPWH On-Going)
View all 114 projects →

4. Implementation

Contract Amount

₱27,914,673.35

Progress

Reported complete (DPWH)

Start Date

May 6, 2018

Target End

October 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.