Flood Control and Drainage20CD0001

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER (BARDIAS SECTION), PHASE VIII, SAN MIGUEL, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG BULO RIVER (BARDIAS SECTION), PHASE VIII, SAN MIGUEL, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱55,294,179.49. Status: Reported complete (DPWH). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Bulo River (Bardias Section), Phase IX, San Miguel, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bulacan 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱55,294,179.49

Progress

Reported complete (DPWH)

Start Date

February 26, 2020

Target End

August 27, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.