GAA 2025 DA FMR25BE0124

CONCRETING OF BRGY. SAN ISIDRO WEST TO BRGY. DIVISORIA FMR, BRGY. SAN ISIDRO WEST AND BRGY. DIVISORIA, STA. MARIA, ISABELA

CONCRETING OF BRGY. SAN ISIDRO WEST TO BRGY. DIVISORIA FMR, BRGY. SAN ISIDRO WEST AND BRGY. DIVISORIA, STA. MARIA, ISABELA is a DPWH-tracked public work in Isabela 1st DEO, Region II. Reported contract value: ₱19,283,099.88. Status: Past target date (DPWH On-Going). Contractor on record: PERUDIAL CONST. Figures trace to dpwh.

Isabela 1st DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Salay Flood Control Structure Section 4, Brgy. Salay, San Agustin, Isabela
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Isabela 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

6 projects · ₱230.7M total · 0 flags

Other projects by this contractor

View all 6 projects →

4. Implementation

Contract Amount

₱19,283,099.88

Progress

Past target date (DPWH On-Going)

Start Date

July 14, 2025

Target End

December 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.