GAA 2025 OO-225I00163

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM), RIZAL RIVER, BABATNGON, LEYTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DOWNSTREAM), RIZAL RIVER, BABATNGON, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱123,725,297.54. Status: Past target date (DPWH On-Going). Contractor on record: AQUALINE CONST CORP FORMERLY: AQUALINE CONST 11555. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 11555

239 projects · ₱17.7B total · 0 flags

4. Implementation

Contract Amount

₱123,725,297.54

Progress

Past target date (DPWH On-Going)

Start Date

June 11, 2025

Target End

June 5, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.