Flood Control and Drainage23HO0252

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO UPPER TALAYONG, BRGY. TUPAS, RONDA, CE

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT SITIO UPPER TALAYONG, BRGY. TUPAS, RONDA, CE is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱94,085,990.97. Status: Past target date (DPWH On-Going). Contractor on record: JCM AMEG BUILDERS CORP FORMERLY: AMEG CONST. Figures trace to dpwh.

Cebu 7th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Wall Structures at Sitio Aransana - Sitio Sulok (Right Side Upstream), Brgy. Mindanao, Malabuyoc, Cebu
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cebu 7th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT PUROK ACACIA (LEFT SIDE), BARANGAY LIBOO, RO

Cebu 7th DEO, Region VII

2025₱99.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF COASTAL ROAD WITH STORM SURGE PROTECTION, BUHATAN-SALVACION, SANTO DOMINGO, ALBAY

Albay 1st DEO, Region V

2022₱95.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT PUROK KALUBIHAN I, BARANGAY LIBOO, RONDA, CE

Cebu 7th DEO, Region VII

2025₱95.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT WALL, BARANGAY BUTONG TO BARANGAY TUPAS, RONDA,

Cebu 7th DEO, Region VII

2025₱95.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTSALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES,CONSTRUCTION OF REVETMENT WALL AT SITIO UPPER TALAYONG, BRGY. TUPAS, RONDA, CE

Cebu 7th DEO, Region VII

2023₱94.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF REVETMENT WALL AT BRGY. TUPAS

Cebu 7th DEO, Region VII

2024₱94.1M
Past target date (DPWH On-Going)
View all 27 projects →

4. Implementation

Contract Amount

₱94,085,990.97

Progress

Past target date (DPWH On-Going)

Start Date

December 27, 2023

Target End

October 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.