Flood Control and Drainage25F00411

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF EMBANKMENT PROTECTION OF BIBIRAO INTAKE DAET-TALISAY RI

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF EMBANKMENT PROTECTION OF BIBIRAO INTAKE DAET-TALISAY RI is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱14,079,836.73. Status: Past target date (DPWH On-Going). Contractor on record: 128 DRAGON CONST AND SUPPLIES. Figures trace to dpwh.

Region V, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

208 projects · ₱3.4B total · 2 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ROAD ALONG DAET RIVER, BARANGAY

Region V, Region V

2025₱96.6M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF BINATAGAN RIVER CONTROL STRUCTURE W/ ROAD (PHASE I)BARA

Region V, Region V

2024₱93.6M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)

Construction of Flood Control Structure along Basud River, Barangay San Jose, Basud, Camarines Norte

BASUD (CAMARINES NORTE), CAMARINES NORTE, Region V

2024₱86.8M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 (OO2): PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE AL

Region V, Region V

2024₱86.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REHABILITATION/IMPROVEMENT OF MANGCAMAGONG -MATOOG-TOOG SEAWALL, BARANGAY MANGCAMAGONG, BASUD, CAMARINES NORTE AND BARANGAY MATOOG-TOOG, MERCEDES, CAMARINES NORTE

Camarines Norte DEO, Region V

2020₱74.9M
Reported complete (DPWH)
View all 208 projects →

4. Implementation

Contract Amount

₱14,079,836.73

Progress

Past target date (DPWH On-Going)

Start Date

March 20, 2025

Target End

July 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.