Roads21L00074

ROAD WIDENING - NABUNTURAN - NEW CORELLA - TAGUM ROAD (NEW CORELLA - TAGUM SECTION), DAVAO DEL NORTE

ROAD WIDENING - NABUNTURAN - NEW CORELLA - TAGUM ROAD (NEW CORELLA - TAGUM SECTION), DAVAO DEL NORTE is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱57,712,477.55. Status: Reported complete (DPWH). Contractor on record: MONOLITHIC CONST. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱57,712,477.55

Progress

Reported complete (DPWH)

Start Date

March 24, 2021

Target End

January 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.