Buildings and Facilities24HE0111

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY GREEN HILLS, SAN FERNANDO, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) -MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY GREEN HILLS, SAN FERNANDO, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱1,969,999.80. Status: Reported complete (DPWH). Contractor on record: PEDXING BUILDERS INC FORMERLY: PEDXING BUILDERS. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage System at Barangay, Gawaygaway, San Remigio, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cebu 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,969,999.80

Progress

Reported complete (DPWH)

Start Date

May 7, 2024

Target End

September 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.