Bridges25HH0137

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY KINASANG-AN, CEBU CITY, CEBU

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE/FACILITIES-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY KINASANG-AN, CEBU CITY, CEBU is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱4,875,750.00. Status: Past target date (DPWH On-Going). Contractor on record: MATROSON BUILDERS. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Kinasang-an, Cebu City, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu City DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,875,750.00

Progress

Past target date (DPWH On-Going)

Start Date

April 10, 2025

Target End

October 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.