Roads25AA0347

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS RDS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF RD, BARANGAY SANGIL, BACARRA, I.N.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS RDS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - IMPROVEMENT OF RD, BARANGAY SANGIL, BACARRA, I.N. is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱4,802,095.27. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JEMIS CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bislak River, Barangay Sangil, Bacarra, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

9 projects · ₱46.9M total · 0 flags

Other projects by this contractor

No sat.

BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTA MONICA, SAN NICOLAS, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱9.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY SAOIT, BURGOS, I.N.

Ilocos Norte 1st DEO, Region I

2025₱4.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS RDS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF RD, BRGY 8 SAN ANTONIO, SARRAT, I.N.

Ilocos Norte 1st DEO, Region I

2025₱4.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS RDS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHAB OF ROAD, BARANGAY 13 LIBNAOAN, PIDDIG, I.N.

Ilocos Norte 1st DEO, Region I

2025₱4.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONST OF ROAD BARANGAY 24 SAN ROQUE, SARRAT, I.N.

Ilocos Norte 1st DEO, Region I

2025₱4.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRA PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS RDS AND/OR BRIDGES FROM THE NATIONAL RD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF RD, BRGY 23 SAN ANDRES, SARRAT, I.N

Ilocos Norte 1st DEO, Region I

2025₱4.7M
Past target date (DPWH On-Going)
View all 9 projects →

4. Implementation

Contract Amount

₱4,802,095.27

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 28, 2025

Target End

May 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.