Roads24EF0038

CONST. OF BATANG-BATANG RIVER IRRIGATION SYSTEM LATERAL E SERVICE ROAD, BARANGAY MALINAO, NARRA, PALAWAN (KATUBIGAN-KALSADA TUNGO SA PATUBIGAN), NARRA, PALAWAN

CONST. OF BATANG-BATANG RIVER IRRIGATION SYSTEM LATERAL E SERVICE ROAD, BARANGAY MALINAO, NARRA, PALAWAN (KATUBIGAN-KALSADA TUNGO SA PATUBIGAN), NARRA, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱46,541,775.00. Status: Past target date (DPWH On-Going). Contractor on record: IVY MICHELLE CONST AND TRADING INC FORMERLY:IVY MICHELLE TRADING. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bono - Bono River Flood Control Structure, Bataraza, Palawan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Palawan 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD, BATARAZA-RIZAL CROSS COUNTRY (SUMBILING-CANIPAAN), PACKAGE B, PALAWA

Region IV-B, Region IV-B

2023₱282.6M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD, PACKAGE B, STA. 3+391.16-STA. 6+097.16, BATAR

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE C, STA. 6+097.16-STA. 9+297.66, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF SANDOVAL-PAJO-(IGANG-IGANG)-SARONG-OCAYAN ROAD PACKAGE A, STA. 0+000.00-STA. 3+391.16, BATA

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF PANAS-TAGBITA DIVERSION ROAD PACKAGE B, STA. 0+000.00-STA. 2+585.00, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.4M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)- CONST. OF PANAS-TAGBITA DIVERSION ROAD, PACKAGE A, STA. 0+000-STA. 2+820, BATARAZA, PALAWAN

Region IV-B, Region IV-B

2025₱279.3M
Past target date (DPWH On-Going)
View all 150 projects →

4. Implementation

Contract Amount

₱46,541,775.00

Progress

Past target date (DPWH On-Going)

Start Date

March 8, 2024

Target End

August 16, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.