Buildings and Facilities20GD0077

CONSTRUCTION/COMPLETION OF BRGY. MULTI-PURPOSE BUILDING, PHASE 2, BRGY. BAYBAY, ROXAS CITY, CAPIZ

CONSTRUCTION/COMPLETION OF BRGY. MULTI-PURPOSE BUILDING, PHASE 2, BRGY. BAYBAY, ROXAS CITY, CAPIZ is a DPWH-tracked public work in Capiz 1st DEO, Region VI. Reported contract value: ₱2,633,232.66. Status: Reported complete (DPWH). Contractor on record: MBM CONST. Figures trace to dpwh.

Capiz 1st DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,633,232.66

Progress

Reported complete (DPWH)

Start Date

October 20, 2020

Target End

March 16, 2021

5. Audit