Flood Control and Drainage23I00020

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SOLANO RIVER (UPSTREAM), BRGY. SAN MIGUEL AND BRGY. ATIPOLO, TANAUAN, LEYTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SOLANO RIVER (UPSTREAM), BRGY. SAN MIGUEL AND BRGY. ATIPOLO, TANAUAN, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱95,658,809.72. Status: Past target date (DPWH On-Going). Contractor on record: PABLO S LABASBAS CONST CORP FORMERLY: PABLOS LABASBAS CONST CORP. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

515 projects · ₱13.3B total · 0 flags

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. SUROK - GAHOY - SAPAO, GUIUAN, EASTERN SAMAR

Region VIII, Region VIII

2023₱144.5M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS TACLOBAN - STA. FE - SAN MIGUEL ROAD, LEYTE

Region VIII, Region VIII

2023₱143.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE ALONG ASUNCION - BENIT SECTION, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱120.5M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY NUEVA ESPERANZA, HINUNANGAN, SOUTHERN LEYTE

Southern Leyte 2nd DEO, Region VIII

2025₱105.6M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING SECONDARY ROADS, WRIGHT - TAFT - BORONGAN RD (SM00172SM)K0875+667 - K0876+511, K0877+525 - K0878+256, K0878+800 - K0879+389

Eastern Samar DEO, Region VIII

2025₱104.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BAGAHUPI - BABATNGON - STA CRUZ - BARUGO - CARIGARA RD. - (S00066LT) K0927+(-348) - K0927+(-310), LEYTE 1ST LD

Region VIII, Region VIII

2023₱101.2M
Reported complete (DPWH)
View all 515 projects →

4. Implementation

Contract Amount

₱95,658,809.72

Progress

Past target date (DPWH On-Going)

Start Date

March 15, 2023

Target End

January 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.