GAA 2025 OO-225CG0066

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONCRETING OF SLOPE PROTECTION AT INUMAN BAKA STA. ANA-ARAYAT PORTION, PAMPANGA PHASE II

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONCRETING OF SLOPE PROTECTION AT INUMAN BAKA STA. ANA-ARAYAT PORTION, PAMPANGA PHASE II is a DPWH-tracked public work in Pampanga 1st DEO, Region III. Reported contract value: ₱91,485,532.02. Status: Past target date (DPWH On-Going). Contractor on record: CHOLO CONST AND TRADING 32138. Figures trace to dpwh.

Pampanga 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pampanga River, (Downstream-Left Bank), Barangay Consuelo, Macabebe, Pampanga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Pampanga 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 32138

136 projects · ₱1.6B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF SLOPE PROTECTION AT SAN ROQUE BITAS CREEK, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2025₱91.7M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES - CONSTRUCTION OF SLOPE PROTECTION STRUCTURE AT PALINLANG CREEK, ARAYAT, PAMPANGA

Pampanga 1st DEO, Region III

2025₱91.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - TERTIARY ROADS - BALIWAG - CANDABA - STA. ANA RD. - K0067+433 - K0067+571, CANDABA, PAMPANGA

Pampanga 1st DEO, Region III

2019₱67.9M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONCRETING OF SLOPE PROTECTION AT INUMAN BAKA STA. ANA-ARAYAT PORTION, PAMPANGA PHASE I

Pampanga 1st DEO, Region III

2025₱64.2M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/ IMPROVEMENT OF CRITICAL SECTION OF STA. CATALINA DIKE EXTENSION, MINALIN, PAMPANGA

Pampanga 1st DEO, Region III

2018₱55.1M
Reported complete (DPWH)
No sat.

FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF SLOPE PROTECTION, MATUBIG CREEK, STA. ANA, PAMPANGA

Pampanga 1st DEO, Region III

2024₱54.9M
Reported complete (DPWH)
View all 136 projects →

4. Implementation

Contract Amount

₱91,485,532.02

Progress

Past target date (DPWH On-Going)

Start Date

June 3, 2025

Target End

February 5, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.